The Central Downtown construction site in Arjan, showing podium slabs and formwork

Subcontract · DUBAI

The Central Downtown

Shuttering & de-shuttering

Site photograph · ABA PRIME

PROJECT OVERVIEW

Shuttering & de-shuttering

ABA PRIME provides superstructure shuttering and de-shuttering works for ATCON Constructions LLC at The Central Downtown in Arjan, Dubai. Our package covers areas D2, D3 and D4 at The Central Downtown, with a dedicated workforce of 30 people. It includes formwork carpentry and related material shifting, with work carried out to the approved project drawings and agreed site programme.

Original project photographs supplied by ABA PRIME.

Location
Arjan, Dubai
Project areas
D2, D3 & D4
Main contractor
ATCON Constructions LLC
Project client
Aqua Skyline Investments Limited
Consultant
Chawla Engineering Consultants
ABA PRIME workforce
30 people
Role
Shuttering subcontractor
Agreement date
13 June 2026

OUR SCOPE ON SITE

Formwork across
the structure.

01

Slabs, columns & beams

Shuttering and de-shuttering of slabs, columns and beams within the assigned project areas, including tie beams and the double-height elements specified in the subcontract.

02

Core walls & stairs

Formwork for core walls and stairs, together with round columns, across the agreed work fronts. The package includes elements from the second podium level to the roof, as defined in the approved drawings.

03

Roof & edge details

Formwork for pour strips, parapets, upstands and downstands, including the roof and elevation details shown in the approved drawings.

04

Carpentry & site coordination

Related carpentry fabrication and material shifting form part of the package. Work-area allocation follows site management approval, with execution coordinated against the consultant-approved specifications and DDA-approved drawings.

LET’S BUILD WHAT’S NEXT

Your vision.
Our commitment.